Customer:
Covidien
LOCATION:
Raleigh, NC
Scope of Work:
Armstrong International developed, engineered, and installed six energy conservation projects at Covidien’s Acetaminophen Facility.
The projects were financed by Armstrong over a five year term. Armstrong provides monthly engineering review and maintenance support for the heat recovery and steam distribution systems.
Upgrade Projects:
-
Engineered and installed eleven condensate contamination sensors/dump valves to dump condensate for boiler protection
-
Engineered and installed an automatic boiler blowdown system
-
Engineered and installed a D/A vent condenser
-
Engineered and installed air compressor heat recovery for boiler air preheat
-
Engineered and installed boiler oxygen trim controls
-
Implemented a steam trap optimization program
Terms:
Five-year engineering and maintenance term began in May 2000.
Benefits:
Armstrong projected annual savings of $364,000 for the projects, but Covidien was able to document in excess of $500,000 in energy savings. Financing, provided by Armstrong, enables savings to immediately offset costs and eliminate a large capital outlay.